Weather Delay Percentage

A schedule-risk KPI for outdoor work. Align delay day definitions with the contract’s weather clause.

Weather % = weather delay days ÷ planned workdays × 100.

Tip: Keep “Weather Delay Days” and “Planned Workdays” on the same basis (period, units, and population) before calculating Weather Delay Percentage.

Cluster: Construction hub · SPI · CPI · Manufacturing hub · Percentage guide

Weather delay percentage is weather-lost workdays relative to planned workdays in the period.

Enter weather delay days and planned workdays for the same window.

Days lost to weather
Planned workdays in the period

Weather Delay %

Understanding Weather Delay Percentage

How we calculate. Weather % = weather delay days ÷ planned workdays × 100. The form uses the same arithmetic as the worked examples on this page. See our methodology and accuracy policy.

Real-world scenario: A typical Weather Delay Percentage case uses weather delay days 6 and planned workdays 60. Enter the same figures below to reproduce the worked path.

What is Weather Delay Percentage?

A schedule-risk KPI for outdoor work. Align delay day definitions with the contract’s weather clause.

  • Same calendar basis
  • Define a weather day
  • Segment by trade

The Formula

Weather Delay Percentage
Weather delay % = (Weather delay days ÷ Planned workdays) × 100

Worked Example

Scenario: 6 weather days of 60 planned workdays.
Step 1: 6 ÷ 60 = 0.1
Step 2: × 100 = 10%
Answer: Weather delay percentage is 10%.

Common Use Cases

  • Schedule updates: weather impact
  • Claims support: delay documentation
  • Seasonal planning: contingency days

Pro Tips

  • Log concurrent delays separately
  • Match contract weather thresholds
  • Don’t double-count weekends

Limitations: Weather Delay Percentage results are educational construction planning aids—not engineering, safety, legal, or cost-estimating advice. Confirm definitions with your project controls, safety, and contract documents. For earned-value SPI/CPI see the Professional hub.

FAQ

Calendar days or workdays?

This form uses planned workdays in the denominator—keep weather days on the same basis.

What if planned workdays is 0?

Weather delay % is undefined—enter a positive planned workday count.

Authoritative References

For construction project controls and safety rate concepts, consult:

  • OSHA — workplace safety resources
  • PMI — project management practices
  • AIA — contract and project delivery context