Safety TRIR

A standard safety rate for contractors and owners. Confirm recordable definitions with OSHA/local rules—this tool is educational math only.

TRIR = (N × 200,000) ÷ total employee hours worked.

Tip: Keep “Recordable Incidents” and “Hours Worked” on the same basis (period, units, and population) before calculating Safety TRIR.

Cluster: Construction hub · SPI · CPI · Manufacturing hub · Percentage guide

TRIR (Total Recordable Incident Rate) annualizes recordable incidents per 100 full-time workers (200,000 hours).

Enter recordable incidents and total hours worked for the same period.

OSHA-style recordables
Total employee hours worked

TRIR

Understanding Safety TRIR

How we calculate. TRIR = (N × 200,000) ÷ total employee hours worked. The form uses the same arithmetic as the worked examples on this page. See our methodology and accuracy policy.

Real-world scenario: A typical Safety TRIR case uses recordable incidents 3 and hours worked 400000. Enter the same figures below to reproduce the worked path.

What is Safety TRIR?

A standard safety rate for contractors and owners. Confirm recordable definitions with OSHA/local rules—this tool is educational math only.

  • Recordables per your safety policy
  • Hours = employee hours worked
  • Result is a rate, not a percent

The Formula

Total Recordable Incident Rate
TRIR = (Recordable incidents × 200,000) ÷ Hours worked

Worked Example

Scenario: 3 recordables; 400,000 hours worked.
Step 1: (3 × 200000) ÷ 400000 = 1.5
Answer: TRIR is 1.5.

Common Use Cases

  • Prequalification: contractor safety
  • Project dashboards: incident rate
  • Owner scorecards: site TRIR

Pro Tips

  • Align recordable criteria
  • Annualize carefully for short jobs
  • Not a substitute for legal reporting

Limitations: Safety TRIR results are educational construction planning aids—not engineering, safety, legal, or cost-estimating advice. Confirm definitions with your project controls, safety, and contract documents. For earned-value SPI/CPI see the Professional hub.

FAQ

Why 200,000?

It represents 100 employees × 40 hours × 50 weeks—the common U.S. TRIR scaling factor.

What if hours worked is 0?

TRIR is undefined—enter positive hours worked.

Authoritative References

For construction project controls and safety rate concepts, consult:

  • OSHA — workplace safety resources
  • PMI — project management practices
  • AIA — contract and project delivery context