Concrete Yield Percentage

A materials control KPI for pours. Distinct from material waste % (scrap/waste of issued goods)—yield focuses on volume reconciliation.

Yield % = placed/measured volume ÷ batched volume × 100.

Tip: Keep “Placed Volume” and “Batched Volume” on the same basis (period, units, and population) before calculating Concrete Yield Percentage.

Cluster: Construction hub · Safety TRIR · CPI · SPI · Percentage guide

Concrete yield percentage compares placed (or measured) volume to batched/ticketed volume.

Enter placed volume and batched volume in the same unit (CY or m³).

Placed or measured volume
Batched/ticketed volume

Concrete Yield %

Understanding Concrete Yield Percentage

How we calculate. Yield % = placed/measured volume ÷ batched volume × 100. The form uses the same arithmetic as the worked examples on this page. See our methodology and accuracy policy.

Real-world scenario: A typical Concrete Yield Percentage case uses placed volume 96 and batched volume 100. Enter the same figures below to reproduce the worked path.

What is Concrete Yield Percentage?

A materials control KPI for pours. Distinct from material waste % (scrap/waste of issued goods)—yield focuses on volume reconciliation.

  • Same volume unit
  • Batched = ticketed plant volume
  • Investigate yields well below 100%

The Formula

Concrete Yield Percentage
Yield % = (Placed volume ÷ Batched volume) × 100

Worked Example

Scenario: Placed 96 CY; batched 100 CY.
Step 1: 96 ÷ 100 = 0.96
Step 2: × 100 = 96%
Answer: Concrete yield is 96%.

Common Use Cases

  • Pour reports: ticket vs place
  • Cost control: short yields
  • QA: volume discrepancies

Pro Tips

  • Account for pump line leftovers
  • Use consistent measurement method
  • Pair with material waste %

Limitations: Concrete Yield Percentage results are educational construction planning aids—not engineering, safety, legal, or cost-estimating advice. Confirm definitions with your project controls, safety, and contract documents. For earned-value SPI/CPI see the Professional hub.

FAQ

Can yield exceed 100%?

Sometimes measurement error or over-excavation makes placed volume look high—verify survey and ticket data.

What if batched volume is 0?

Yield % is undefined—enter a positive batched volume.

Authoritative References

For construction project controls and safety rate concepts, consult:

  • OSHA — workplace safety resources
  • PMI — project management practices
  • AIA — contract and project delivery context