COCOMO Schedule

Nominal schedule from Basic COCOMO. Compressing below this increases risk and often cost.

Schedule months = 2.5 × person-months^0.38.

Tip: Enter a realistic “Effort (Person-Months)” value, then compare the COCOMO Schedule result to the worked example on this page.

Cluster: Software Development hub · DevOps hub · Percentage guide

COCOMO Basic converts estimated person-months into a nominal development schedule (months).

Enter effort in person-months (e.g. from COCOMO effort).

Estimated development effort

Schedule (Months)

Understanding COCOMO Schedule

How we calculate. Schedule months = 2.5 × person-months^0.38. The form uses the same arithmetic as the worked examples on this page. See our methodology and accuracy policy.

Real-world scenario: Effort estimate of 100 person-months. Use those inputs in the COCOMO Schedule form to verify the on-page formula.

What is COCOMO Schedule?

Nominal schedule from Basic COCOMO. Compressing below this increases risk and often cost.

  • PM = person-months of development effort
  • Output is calendar months of development
  • Staffing ≈ PM ÷ months as a rough average

The Formula

COCOMO Basic Schedule
Duration (months) = 2.5 × (PM)^0.38

Worked Example

Scenario: Effort estimate of 100 person-months.
Step 1: PM = 100
Step 2: 100^0.38 ≈ 5.75
Step 3: Schedule = 2.5 × 5.75 ≈ 14.39 months
Answer: Nominal schedule is about 14.39 months.

Common Use Cases

  • Roadmaps: first-pass timelines
  • Staffing: average headcount hints
  • Risk talks: aggressive compression

Pro Tips

  • Don’t force impossible compression
  • Add integration/test buffers outside the model
  • Use with effort estimate

Limitations: COCOMO Schedule results are educational software estimation aids—not bids, contracts, or performance scores. Calibrate models to your organization’s history.

FAQ

Is this calendar time or work months?

COCOMO schedule is development duration in months; staffing is a separate decision.

What if PM is 0?

Schedule is 0—enter positive effort.